REALIZATION OF ADJUSTMENT WORKS OF THE INDUSTRIAL PURIFICATION PLANT FOR JRS SILVATEAM INGREDIENTS S.R.L.
BRIEF DESCRIPTION OF THE INTERVENTION:
The revamping of the purifier affects the area where the plant currently stands, with replacement and modifications of equipment and pipes.
In the first phase of the start of the works, the Denitrification tank was converted into an Oxidation tank by installing the air diffusion network.
In the equalization basin and in the denitrification basin (new), submerged electric mixers were installed complete with support brackets.
Additional equipment installed and tested are: dynamic thickener and its piping, DAF and its piping, air blowers and manifolds, electric pumps and valves.
CLIENT:
JRS Silvateam Ingredients S.R.L.
OBJECT OF THE INTERVENTION:
Implementation of adaptation works of the industrial purification plant for JRS Silvateam Ingredients S.R.L.
AMOUNTS OF WORKS:
The final amount of the work is € 477,000.00